Scunthorpe General Hospital
-
Sector
Blue Light
-
Duration
40 Weeks
-
Location
40 Weeks
-
Form of Contract
-
Overview
Britcon carried out the refurbishment of 2 first floor wards including the construction of roof top plant rooms to house the new ventilation plant.
Britcon have recently undertaken the refurbishment of 2 first floor wards including the construction of roof top plant rooms to house the new ventilation plant. The project was split into 2 phases with a 2 week decant period for the client. All undertaken whilst the remaining adjacent hospital wards and areas remained in use.
The project briefly comprises the internal refurbishment of Wards 16 & 17 including link corridor and toilets.
Works include demolition of existing masonry walls and the building of new partition walls resulting in a new lay out; works include new windows, new ceilings, fixtures fittings and decoration and new drain runs etc.
The project also includes substantial stripping out of existing M&E works and the replacing of new Mechanical/Plumbing and Electrical elements.
The project also includes major re-roofing works. The work will be undertaken on a phased basis each of a period of 16 weeks with a two week decant period between each phase.